President of Belarus Alexander Lukashenko is on a working visit to Dobrush today, reports BELTA correspondent.

The Head of State will be briefed on the implementation of the investment project for the technical re-equipment of the Dobrush Paper Mill "Hero of Labour". Construction of a plant for the production of coated and uncoated cardboard with a capacity of 200 thousand tons of cardboard per year began here back in 2012, but the work was never completed. The facility has been mothballed.

Last year, the Council of Ministers approved a scheme for the completion of the project in separate commissioning complexes with the involvement of specialized organizations as contractors for each area. The plant is planned to be commissioned in 2020, and in 2022 it is expected to reach its design capacity.

How it all began

Initially, it was expected that the investment project for the re-equipment of the mill would be completed in 2015. However, this was not done, as the Chinese general contractor, Xuan Yuan company, repeatedly missed deadlines due to financing problems. In 2018, the contract with it was terminated.

The total cost of the plant was almost $350 million. Since the start of the project, the general contractor had been paid over $265 million. The remaining credit funds (about $83 million) remained unutilised and, at the request of the Ministry of Finance, were offset by the China Development Bank against the principal debt repayment.

How much money is needed to launch the plant