September 10, Lepel /Own correspondent/. Along Shkolnaya Street, in addition to residential areas of individual and multi-apartment buildings, a number of institutions are located. The general contractor for the capital repair was KUPV ZhKG "Lepel". Since road construction is a specific type of activity, it was entrusted to Road Construction Department No. 34.
September 10, Lepel /Own correspondent/. Along Shkolnaya Street, in addition to residential areas of individual and multi-apartment buildings, a number of institutions are located.
The general contractor for the capital repair was KUPV ZhKG "Lepel". Since road construction is a specific type of activity, it was entrusted to Road Construction Department No. 34.
The road workers undertook to perform the entire cycle of work from design to handover to the customer.
Laying asphalt pavement is a routine task for road workers. For this, they have all the necessary machinery, and importantly, their own asphalt concrete plant, which can produce up to 700 tons of asphalt concrete mix per shift. On the carriageway, asphalt with crushed stone content with an average thickness of four centimeters was laid on the old asphalt pavement, and on the sidewalk – asphalt on clean gravel with a thickness of five centimeters. A lot of asphalt was laid under the parking lots. Since a new location was allocated for them, the pavement there consists of two layers, six and four centimeters thick – a total of a ten-centimeter asphalt layer.
The most labor-intensive operation was the installation of concrete curbs. Such a block weighs 80 kilograms. Each had to be moved and installed manually! Road workers Arkady Dragun and Anatoly Kostyukovich coped excellently with the task.
The chief engineer of RCDU-34, Nikolai Sadovnikov, spoke about an incident where a cable providing telephone communication for the entire microdistrict – 200 pairs of wires! – was almost damaged. It had to be buried another half a meter deeper. Therefore, subsequently, communication technicians went with equipment, checked where the cables were laid, and placed markers. In those places, road workers did not use excavators but used shovels. The gas cover – a special plug crane used to shut off gas supply in mains in case of an accident or emergency – also had to be buried deeper. This was already handled by the gas workers.
In addition to the aforementioned employees, the management of RCDU-34 noted the motor grader operator Alexander Khanyak, asphalt paver operator Leonid Yarshov, and others – an excellent team was assembled.