Customer of the planned activity: State Environmental Institution "Berezinsky Biosphere Reserve".
Customer of the planned activity: State Environmental Institution "Berezinsky Biosphere Reserve".
Legal address: 3, Tsentralnaya Street, Domzheritsy village, Lepel District, Vitebsk Region, 211188
Postal address: 3, Tsentralnaya Street, Domzheritsy village, Lepel District, Vitebsk Region, 211188
Email address: info@berezinsky.by
Telephone/Fax: +3750213137742.
Work schedule for public discussions of the Environmental Impact Assessment (EIA) report:
|
Type of Work |
Execution Period |
|
Development of the EIA Programme |
from 19.09.2022 to 23.09.2022 |
|
Preliminary notification of citizens and legal entities about the planned activity |
from 07.10.2022 to 21.10.2022 |
|
Survey of the planned activity site and adjacent territory |
from 05.09.2022 to 09.09.2022 |
|
Preparation of the EIA report |
from 19.09.2022 to 03.09.2022 |
|
Establishment of a commission for the preparation and conduct of public discussions |
from 24.10.2022 to 28.10.2022 (at least 3 working days before the notification is published) |
|
Notification of citizens and legal entities on the commencement of public discussions |
from 01.11.2022 to 01.12.2022 |
|
Familiarisation of citizens and legal entities with the ESIA report |
from 01.11.2022 to 01.12.2022 |
|
Receipt of appeals from citizens and legal entities regarding the need to hold a meeting on discussion of the EIA report |
from 01.11.2022 to 14.11.2022 (10 working days from the date of notice publication) |
|
Notification of citizens and legal entities on the date and venue of the meeting for the discussion of the EIA report* |
within 5 working days from the date of application by citizens and (or) legal entities |
|
Holding of the meeting for the discussion of the EIA report* |
in accordance with the notice of the meeting for the discussion of the EIA report |
|
Drawing up of the meeting minutes* |
within 5 working days from the date of the meeting |
|
Formalisation of the results of public discussions |
from 01.12.2022 to 14.12.2022 (within 10 working days from the date of completion of discussions) |
|
Revision of the EIA report taking into account the comments and proposals of citizens and legal entities** |
within the EIA period by suspending the EIA procedure (if necessary) |
* - will be carried out in case of public request for the necessity of holding a meeting;
** - will be carried out in case of necessity.
General characteristics of the planned activity and alternative options for its location and (or) implementation:
The "Domzheritsy" woodworking shop and the constructed boiler house with drying units are located at: Vitebsk region, Lepel district, Domzheritsy village, Polevaya St., 1A.
The designed buildings and structures will be located on the land plot for the construction and servicing of the facility within the territory of the State Nature Protection Institution "Berezinsky Biosphere Reserve" "Reconstruction of the "Domzheritsy" Woodworking Shop with expansion of the production base, area 1.8701 ha".
The "Domzheritsy" woodworking shop houses existing buildings and structures: Woodworking Shop 1, Woodworking Shop 2, a workshop for finishing unedged lumber, a wood drying section. A "WALTER" round timber processing line has been installed, in addition to the previously installed line for
round timber processing "MEBOR". The line capacity allows for processing up to 110.0 cubic meters of round timber per day with a 12-hour working shift. The main products manufactured using this equipment are edged lumber and pallet boards. Both lines include chippers designed for processing sawmill waste into wood chips.
Additionally, the workshop houses a "SERRA Montana" ME90 band saw, an MG-2000 band saw, and a lumber finishing line consisting of 2 machines.
The "Domzheritsy" woodworking shop also features equipment for wood antiseptic treatment.
The following buildings and structures are planned: a boiler house, a drying kiln, local treatment facilities, a DGU (diesel generator unit) site, and a finished goods warehouse.
A projected attached boiler house (two KVT-0750E hot water boilers with a thermal output of 750 kW each) is planned as the heat source for the drying units, heating system, and hot water supply. It will operate on fuel wood chips in accordance with Technical Specifications TU BY 100145188.003-2009.
Furthermore, it is planned to install treatment facilities manufactured by "Belpoliplastik" BelECOline K15 or an equivalent with a capacity of 15 l/s.
DGU site. An AD104S-T400-2RP (MMZ) diesel generator will be installed.